EMT Practice Test
1. Question Content...
Question15: Which of the following statements are true regarding program scope statement?
Question27: What does RACI stand for?
Question37: When is the lessons learned document updated?
Question66: Small changes that bypass the organization's change control procedures are called ____.
Question68: Which of the following documents describes the details for each component in the WBS?
Question90: What is the formula to determine earned value (EV) for a program?
Question106: What percentage of communication is nonverbal?
Question109: In which of the following processes is the program charter created?
Question114: What is the other name for critical delivery dates?
Question115: Which one of the following is the best definition of program quality?
Question120: Which of the following increases when one fast tracks the project?
Question146: Who makes Go/No-Go decisions during phase gate reviews?
Question149: All of the following are benefits of a program except for which one?
Question156: Small changes that bypass the organization's change control procedures are called ____.
Question164: Which of the following increases when one fast tracks the project?
Question179: After program closure, the lessons learned document becomes the part of?
Question185: What does CPI value less than 1.0 indicates?
Question215: When should a program manager approve the closure of a component project?
Question248: Which of the following is used to build consensus through rounds of anonymous surveys?
Question256: Which of the following documents sets the project objectives?
Question263: Which one of the following is the best example of transference?
Question266: What does CPI value less than 1.0 indicates?
Question275: In which of the following processes is the program charter created?
Question288: Performing quality assurance in a program can result in which one of the following?
Question293: Which of the following documents sets the project objectives?
Question296: After program closure, the lessons learned document becomes the part of ____?
Question297: Which of the following documents describes the details for each component in the WBS?
Question306: Who prepares the statement of work (SOW) for external projects?

