Question1: You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

Question2: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Question3: In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Question4: A program sponsor is concerned about the status of high-priority risks and budget variances.
The program manager should refer to which of the following?

Question5: What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

Question6: Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs which need is at the top of the hierarchy?

Question7: You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?

Question8: One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.
If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?

Question9: A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

Question10: What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

Question11: Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.

Question12: You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Question13:
The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee.
What do the current findings show?

Question14: Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Question15: Which of the following statements are true regarding program scope statement?

Question16: You are the program manager for your organization. You're currently working with the program director, Nancy Holmes, to define a new program and the benefits the program should create. Of the following, which is the best definition of a benefit a program creates?

Question17: You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Question18: Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

Question19: Molly is the program manager for her organization and she is creating a program plan that defines the benefits of the program and how her program and team will create the benefits for the organization. What plan is Molly creating in this scenario?

Question20: A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder?

Question21: An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.
What should the program manager do to ensure that the remaining 10 component projects stay on track?

Question22: You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

Question23: You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?

Question24: Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.

Question25: You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

Question26: Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

Question27: What does RACI stand for?

Question28: If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?

Question29: What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Question30: You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any QUESTION NOs the vendors may have about the project. What is this meeting called?

Question31: You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?

Question32: You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Question33: Your program has a budget at completion of $1,550,000 and is expected to last one year. Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses. They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

Question34: Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Question35: The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's life cycle.
Which of the following would the customer be interested in reviewing?

Question36: You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled.
Which one of the following is not something you'll have to monitor and control as a program manager?

Question37: When is the lessons learned document updated?

Question38: A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?

Question39: There are five stages of team development. At which stage are there likely to be disagreements and struggle for roles in the program team?

Question40: An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?

Question41: Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

Question42: You are working with Sam, a project manager on one of the projects within your program. Sam doesn't understand all of the rules and procedures that he's required to do as a project manager in your program. What are the rules and procedures called in project that Sam must abide by?

Question43: You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

Question44: You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?

Question45: Harriet is the program manager of a large program that has a high profile and visibility in her organization.
Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

Question46: The number of emerging risks increases in a component project and the program manager falls behind in reviewing and approving the plans. This impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?

Question47: All of the following information is defined in the program statement of work except for which one?

Question48: You are trying to determine if you should buy or build a solution for your program. If you build the solution it'll cost you $45,000 to create and $7,000 per month to support. A vendor reports that they can create the solution for you for $1,000 but you'll have to pay them $9,000 per month to support the solution. Should you buy or build this solution?

Question49: All of the following are resources that need to be monitored and controlled except for which one?

Question50: An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?

Question51: You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?

Question52: Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?

Question53: You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

Question54: Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentation. Marty has written the final project report, released the project team, and completed the lessons learned documentation. What else should Marty do in the closure of the NHK Project?

Question55: A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning, the program manager should consider which of the following stakeholders aspects?

Question56: A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.
At the next stakeholder meeting, what should the program manager present to address their concerns?

Question57: As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

Question58: A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.
What should the program manager do to address the risk?

Question59: Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

Question60: You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Question61: You are the program manager for a large program in your matrix organization. You need to define when the resources in your program will be brought into the program and then released from the program so that the project managers, operational managers, and your program team can plan accordingly. What program management plan defines when resources are needed, how the resources will be obtained, and how the resources may be released from the program?

Question62: You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

Question63: A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component project requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.
What is a critical component of the Program Schedule Management Process?

Question64: A program is near completion and the benefits will be delivered shortly. The program manager prepares to initiate program closeout activities to release the program resources.
Before initiating closeout and releasing the resources, what should the program manager do?

Question65: You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

Question66: Small changes that bypass the organization's change control procedures are called ____.

Question67: You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program.
To whom will you report to in this program?

Question68: Which of the following documents describes the details for each component in the WBS?

Question69: Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Question70: Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

Question71: Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document is Molly writing?

Question72: Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

Question73: After a company's senior executive management meeting, the CEO issues a mandate to automate a new- client on-boarding process that would effectively eliminate the current, manual, paper-based process. The assigned program sponsor selects a program manager.
Both the program sponsor and the program manager must ensure that the program charter contains which of the following?

Question74: Stakeholders ask the program manager to assess reasons for the project's delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.
The program manager distributes information in accordance with which of the following?

Question75: Which of the following directs the improvement efforts to those areas that will have the biggest impact?

Question76: You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Question77: A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager's next step?

Question78: You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

Question79: Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Question80: Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

Question81: You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

Question82: In a program, management would like to consider the present value for each year a program creates a return on investment. What program selection method is management using?

Question83: A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Question84: You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Question85: Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

Question86: A program manager prepares the program for review to secure funding by senior management.
Which of the following must the program manager identify when creating the program charter?

Question87: You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Question88: You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

Question89: You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

Question90: What is the formula to determine earned value (EV) for a program?

Question91: There are 1,500 doors to be installed in Tom's program. Each of the 1,500 doors is required by the building code to swing into the room rather than swing out into the hallways. It has come to Tom's attention that part of the team installing the doors has installed nearly 200 doors to swing into the hallway rather than into the rooms. Tom instructs the team to fix the problem. What type of action has Tom taken in this instance?

Question92: An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?

Question93: You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope.
If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

Question94: Which of the following statements are true regarding program scope changes? (Choose three.)

Question95: You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?

Question96: What cost estimating approach uses the work breakdown structure to create a cost estimate?

Question97: Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

Question98: A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?

Question99: A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent
$620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

Question100: You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance?

Question101: You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

Question102: Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.

Question103: You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Question104: A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.
Where should the program manager document this?

Question105: The program charter for a new, five-component program has been approved.
What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?

Question106: What percentage of communication is nonverbal?

Question107: You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Question108: What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of return is five percent?

Question109: In which of the following processes is the program charter created?

Question110: A program manager initiates a developmental program. Significant resources and funding are required for early activities until the program cost and budget estimates are complete.
What should the program manager do to understand the financial environment?

Question111: As a Program Manager, you decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

Question112: Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB.
What document should you provide to Hal?

Question113: A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline.
What key elements should be included in the benefits register to achieve this goal?

Question114: What is the other name for critical delivery dates?

Question115: Which one of the following is the best definition of program quality?

Question116: The program manager plans to address a negative cost variance generating a red flag in the program management status report.
What should the program manager do?

Question117: You are the program manager for your organization. Part of your role as the program manager is to train John, a new program manager, on the program processes within a program. John is confused as to when the program team can be acquired in the program management lifecycle. When will the program team be acquired for a program?

Question118: Complete the following phrase about quality management: Quality isinto a program, notinto a program.

Question119: What duration compression technique typically adds risk when it's used during a program?

Question120: Which of the following increases when one fast tracks the project?

Question121: After new private equity owners acquire an enterprise, they want to improve its value by reducing costs. A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed. A strategic component project presents significant risk to organizational objectives due to its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility. Implementation of this component project may now begin, but is already one month behind schedule. The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?

Question122: The chief executive officer (CEO) informs the program manager that the delivery date for project A must be compressed by two months to accommodate market needs. Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?

Question123: Which of the following individual should respond to the risk with the preplanned risk response?

Question124: A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?

Question125: Mary has just completed a large program for her organization. What should Mary now do with the program records that she has created throughout the program?

Question126: An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?

Question127: A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.
What should the program manager do next?

Question128: You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

Question129: Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

Question130: You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Question131: Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Question132: Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

Question133: At what point in the project is the risk of failing to achieve the project objectives the greatest?

Question134: You are the program manager for your organization and you're trying to determine if you buy or build a software solution for your organization. If you build the solution it'll cost you $75,000 to create and it'll cost you $12,000 per month to support. If you hire a vendor they can build the solution for $63,000 but their solution will cost you
$15,500 per month to support. How many months would you have to use your in-house solution to equate to the cost of the vendor's solution?

Question135: Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

Question136: You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

Question137: You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end- of-phase review management is completing on your project?

Question138: During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?

Question139: You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?

Question140: You are the program manager for your organization. You're currently working with the program director, Nancy Holmes, to define a new program and the benefits the program should create. Of the following, which is the best definition of a benefit a program creates?

Question141: You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done. You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

Question142: You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Question143: A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Question144: You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Question145: Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Question146: Who makes Go/No-Go decisions during phase gate reviews?

Question147: During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Question148: You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you've made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?

Question149: All of the following are benefits of a program except for which one?

Question150: You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Question151: Wanda is the program manager for her organization. Her program team consists of resources from across the organization - many of whom have not worked together before. Wanda thinks that she'll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?

Question152: Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?

Question153: Which of the following information gathering techniques is described in the statement below?
"Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment."

Question154: You are the program manager for the NHQ Program. Your program has a budget of
$4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?

Question155: Which of the following statements is the most accurate when it comes to program change requests for the program scope?

Question156: Small changes that bypass the organization's change control procedures are called ____.

Question157: The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.
What should the program manager do next?

Question158: You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

Question159: You are identifying stakeholders for your program to create new software for your organization. The software will affect the ordering by the customer, the manufacturing of the product, inventory, and account management. Sarah, a key stakeholder in your program, is skeptical of one application affecting so many parts of the organization. She prefers that several applications be created instead of the approach your program will take. In stakeholder identification how would you categorize Sarah?

Question160: You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

Question161: What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?

Question162: Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?

Question163: You are the program manager for your organization and are planning the composition of the project team. In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?

Question164: Which of the following increases when one fast tracks the project?

Question165: A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider.
What should the program manager do before assigning the project managers?

Question166: You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Question167: You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?

Question168: A program manager is responsible for constructing a US$50 million building. Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However, heavy demand for steel is causing price increases and delivery delays. If this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years.
What is the expected time of delivery?

Question169: You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow all stakeholders to review what has been submitted in an attempt to find consensus?

Question170: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Question171: Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?

Question172: You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

Question173: You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Question174: You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Question175: A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?

Question176: Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Question177: You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort. The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another. You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

Question178: An IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?

Question179: After program closure, the lessons learned document becomes the part of?

Question180: What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

Question181: You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Question182: A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?

Question183: A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?

Question184: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses.
They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

Question185: What does CPI value less than 1.0 indicates?

Question186: Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

Question187: When a change enters your program requirements you must update all of the following documents except for which one?

Question188: Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

Question189: In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors.
There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Question190: Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

Question191: Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

Question192: A program manager recognizes that a successful resource being used in project A could also be used in project B.
What should the program manager do first to leverage the utilization of this resource?

Question193: As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

Question194: You are the program manager for your organization. This program will last for two years and has eight projects.
The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon.
What is management horizon also known as?

Question195: Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

Question196: An organization supports both programs and projects for various industries. What is a portfolio?

Question197: You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

Question198: The program manager defines the program objectives, requirements, and develops a high-level road map.
To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?

Question199: Which of the following statements is the most accurate when it comes to program change requests for the program scope?

Question200: A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?

Question201: A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk.
What should the program manager do to monitor and control the supplier?

Question202: A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?

Question203: A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review.
What is the other part of the review?

Question204: You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

Question205: Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."

Question206: A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.
What technique could the program manager use to gain more input from this project manager?

Question207: Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology. Company B is excited about the joint marketing opportunity. Company A's component Quality Assurance team has expressed concerns to you, the program manager, that the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal. Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled.
What is your MOST appropriate next step?

Question208: Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction.
These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?

Question209: You are trying to determine if you should buy or build a solution for your program. If you build the solution it'll cost you $45,000 to create and $7,000 per month to support. A vendor reports that they can create the solution for you for $1,000 but you'll have to pay them $9,000 per month to support the solution. Should you buy or build this solution?

Question210: You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

Question211: You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?

Question212: Which one of the following is NOT a component of the risk monitoring and controlling process?

Question213: Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

Question214: A software development program will launch iterative versions of new software called Alpha over two years.
Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?

Question215: When should a program manager approve the closure of a component project?

Question216: Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

Question217: As a program manager you must also understand the project management lifecycle and the project lifecycle.
What is the difference between the two?

Question218: A program has been established and preparation is complete.
Component projects are planned as a part of which of the following?

Question219: During the execution phase of a program, a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects.
What should the program manager do to address the situation?

Question220: Which of the following is responsible to sign off on the closure documents of a project?

Question221: Terri is the program manager for her organization and she's working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

Question222: Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?

Question223: After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?

Question224: A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?

Question225: You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Question226: You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Question227: Complete the following phrase about quality management: Quality is ____ into a program, not ____ into a program.

Question228: Program management has several themes that the program manager must be aware of.
Which one of the following is not a program management theme?

Question229: You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance datA.
In which of the following processes are you working on?

Question230: A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits that the program should deliver and has requested that the program manager determine when incremental benefits can be realized.
What should the program manager do first?

Question231: You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

Question232: Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Question233: A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent $620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time.
Based on this information which type of performing is present in this scenario?

Question234: Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Question235: A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Question236: You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?

Question237: Which of the following statements are true regarding the Monitoring and Controlling Program Risks process?
Each correct answer represents a complete solution. Choose all that apply.

Question238: You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

Question239: You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

Question240: Your program has a budget at completion of $1,550,000 and is expected to last one year. Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Question241: A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).
What should the program manager update?

Question242: In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

Question243: One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.
If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?

Question244: An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.
In what phase is the risk management plan created?

Question245: A program manager is leading a program to transform an organization's sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance.
A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.
What should the program manager do next?

Question246: According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

Question247: You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Question248: Which of the following is used to build consensus through rounds of anonymous surveys?

Question249: During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?

Question250: You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Question251: A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

Question252: A component project of a program is completed, and will provide the intended incremental benefits.
How should the program manager proceed with the component transition?

Question253: You are the program manager for your organization. Your current program, which has just started, has eight projects and many of the projects share resources such as equipment and people. Management has asked that you identify when the project resources will be utilized on each project within your program. They are worried some resources may be idle or overscheduled. What approach can you use to consider the availability of resources when the project managers begin sequencing their project activities?

Question254: You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

Question255: You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Question256: Which of the following documents sets the project objectives?

Question257: Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

Question258: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses.
They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

Question259: A program sponsor is concerned about the status of high-priority risks and budget variances.
The program manager should refer to which of the following?

Question260: You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?

Question261: Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?

Question262: Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Question263: Which one of the following is the best example of transference?

Question264: You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program. To whom will you report to in this program?

Question265: What would prevent a program manager from completing program closure once a program has been completed?

Question266: What does CPI value less than 1.0 indicates?

Question267: Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?

Question268: A large infrastructure development program involves three road construction projects, two sewage line construction projects, and one project to lay underground electric cables. During a program meeting, the project manager of a road construction project communicates that a project risk related to the interdependency with a sewage line project has crossed its risk threshold.
What should the program manager do next?

Question269: Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?

Question270: During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.
What should the program manager do?

Question271: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Question272: Which one of the following is not an output of the direct and manage program execution process?

Question273: The program manager must define the program and understand the organization's target market and customer needs.
What should the program manager do first?

Question274: Which one of the following is not an output of the direct and manage program execution process?

Question275: In which of the following processes is the program charter created?

Question276: Joan is the program manager for her organization. Management has asked her to create a centralized reporting system to capture information on program work, risks, changes, benefits management, and other aspects of the program. What solution can Joan implement to capture, communicate, and record the information management wants?

Question277: An organization supports both programs and projects for various industries. What is a portfolio?

Question278: A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

Question279: A program delivers incremental benefits, but is far from closure. The company completes an acquisition and defines new strategic objectives.
What should the program manager do next?

Question280: You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

Question281: How does a portfolio's collection of work differ from that of a program's collection of work?

Question282: You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work
20 hours per week on the program. What is this limit of resource hours in a time period known as?

Question283: A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Question284: A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However, the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?

Question285: You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Question286: You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization.
Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

Question287: A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Question288: Performing quality assurance in a program can result in which one of the following?

Question289: Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?

Question290: In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country
B. The program manager creates the program team by identifying the required project management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with the program's needs?

Question291: You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

Question292: You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Question293: Which of the following documents sets the project objectives?

Question294: A program manager is working on benefits. The program team created and updated a benefits register earlier in the program.
The benefits register should include which of the following?

Question295: Which of the following can be used to help you or other project managers on future projects?

Question296: After program closure, the lessons learned document becomes the part of ____?

Question297: Which of the following documents describes the details for each component in the WBS?

Question298: You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Question299: You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

Question300: Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

Question301: In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Question302: You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Question303: Rick is a Program Manager for a large construction program. The program contains four projects.
Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?

Question304: In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Question305: You are the program manager for your organization and you are dealing with your program stakeholders. You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

Question306: Who prepares the statement of work (SOW) for external projects?

Question307: A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?

Question308: You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:
Cost

Schedule

Experience

Certification

Warranty

Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?